The Early Learning Centre is beginning to show the wonderful place it will become. With all of the brickwork finished and the near completion of the roof. This week the electrical and data services installation is beginning as the internal wall frames are now in place.

The concrete slab in the K-3 classroom block is now poured and drying. We look forward to seeing the steelwork appear next week.

In our car park, the kerbing and guttering are now all in place and we have large garden beds around them. We currently are preparing for the surfacing to begin.

Last week, we took a moment to embrace the beautiful views from the classrooms and the playground. The views provide an inspiring environment surrounding the school, which all students can enjoy.